| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Environmental clearances for the project | B: 165. Obtain environmental clearances for project | 08/31/2020 | 08/31/2020 | |
| Effective implementation management and timely contract administration | C: 119. Manage and Administer project | 08/31/2020 | 08/31/2020 | |
| Completed 2016-17 Annual Report | D: 132. Prepare and submit Progress Report for June 2017 to May 2018 | 01/31/2020 | 12/31/2019 |
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | |||||||
| B | 165 | Obtain environmental clearances for project | |||||||
| C | 119 | Manage and Administer project | |||||||
| D | 132 | Prepare and submit Progress Report for June 2017 to May 2018 |